Barcaldine-Aramac Road, rehabilitate and widen pavement
An additional 5km of Barcaldine-Aramac Road has been widened to improve travel conditions.
This road is an important transport link for the cattle and agriculture industries and provides access to Townsville and other major centres in northern Queensland.
A works program of 5 separate projects executed from 2021 to 2023 has previously seen over 26km of this road broadened to a contemporary standard width of 8m.
This latest phase of work builds on that achievement, with another 5km of the road widened to 8m, further improving safety and travel times for everyone who depends on this important transport link.
Benefits
- Improves safety
- Increases capacity
- Improves network efficiency
- Improves flood immunity
- Reduces travel time
- Contributes to economy
- Contributes to regional growth
- Reduces maintenance
Key features
- Widened and sealed 5km of narrow sections to 8m.
- Improved safety.
- Improved travel times.
- Improved wet weather access.
- Additional overtaking opportunities.
Funding
The 2 projects were funded separately:
- Barcaldine-Aramac Road (Section 1), rehabilitate and widen pavement—$2.377 million. Fully funded by the Queensland Government.
Investment ID: 2109074 - Barcaldine-Aramac Road (Section 2), pavement rehabilitation—$3.023 million. Fully funded by the Queensland Government.
Investment: ID 2983865
- Total investment
- $5.4 million
- Queensland Government
- $5.4 million
Current status
The projects were delivered collectively by local crews from Barcaldine Regional Council. Works commenced in June 2024 and were completed in December 2024.