Consultation summary

Consultation summary

Back to Bruce Highway (Gympie – Maryborough), Tiaro Bypass, construct bypass project webpage

Overview

The following is a timeline of consultation activities that occurred and which stakeholder groups were involved.

February 2019

Project update and feedback form was distributed seeking feedback on the 2 options under investigation (bypass and existing highway upgrade).

Feedback suggested a bypass was supported, but economic impacts on Tiaro were a significant concern. This feedback heavily influenced the consultation process and project moving forward.

Stakeholder groups involved: Bauple, Tiaro, Owanyilla and Talegalla Weir communities.

Back to top

November 2019

Project update distributed explaining the bypass decision and the consultation process moving forward, inviting residents to nominate to join the Tiaro Community Working Group.

We received 18 nominations and all nominations were accepted. 3 nominees withdrew prior to commencement of meetings. The remaining working group members comprised a mix of residents, landowners and business owners from Tiaro and surrounds, including 2 Bauple community members, who remain active participants.

Stakeholder groups involved: Bauple, Tiaro, Owanyilla and Talegalla Weir communities.

Back to top

March 2020

The Tiaro Community Working Group was formed and commenced meetings and workshops with us and the Fraser Coast Regional Council to provide input into the bypass draft concept design on behalf of the community, and developed a community plan for Tiaro.

Fraser Coast Regional Council will also be developing a Community Plan with Bauple. The Tiaro Community Plan was fast-tracked in recognition of the direct economic impact of the bypass on Tiaro, and to enable Tiaro to position itself to realise its social and economic potential in a post-bypass environment.

Stakeholder groups involved: Tiaro Community Working Group members.

Back to top

September 2020

Project update distributed presenting the highway alignment within the bypass corridor study area, explaining how the alignment had been selected, and advising of the next steps for the project.

Stakeholder groups involved: Bauple, Tiaro, Owanyilla and Talegalla Weir communities.

Back to top

December 2021

Project update distributed showcasing the draft concept design and providing contact information for feedback and enquiries.

Stakeholder groups involved: Bauple, Tiaro, Owanyilla and Talegalla Weir communities.

Public meeting in Bauple.

Stakeholder groups involved: Bauple, Tiaro, Owanyilla and Talegalla Weir communities.

Back to top

July 2022

Community information sessions held on 22, 23 and 24 July 2022.

Stakeholder groups involved: Bauple, Tiaro, Owanyilla and Talegalla Weir communities.

Back to top

Additional consultation activities

In addition to the broad community consultation activities outlined above, the project team has met with the Tiaro Chamber of Commerce and the Bauple Progress Association, at their request and arranged follow-up meetings with stakeholders that the Bauple community identified as its preferred representatives.

The project team also met with landowners and other key stakeholders throughout development of the project. 

Back to top

Last updated: 13 November 2025