Location
Perseverance Creek
Timing
Construction commenced in March 2025 and is expected to take around 12 months to complete, weather and construction conditions permitting
Status
Construction

Esk-Hampton Road, Perseverance Creek, replace culvert

This project involves replacing a failing culvert on Esk-Hampton Road at Perseverance Creek.

A temporary 2-lane side track is being constructed adjacent to the damaged culvert to allow Esk-Hampton Road to remain open during the culvert replacement works.

The side track is being constructed prior to the culvert being replaced and once complete, traffic will be diverted onto the side track to allow culvert replacement works to commence.

Benefits

  • Improves safety
  • Increases capacity
  • Improves network efficiency
  • Improves flood immunity
  • Contributes to economy
  • Contributes to regional growth
  • Reduces maintenance

Key features

  • Elimination of a failing structure on the road network
  • Improved safety
  • Increased road resilience

Funding

$12.16 million, over 3 years, has been committed to the culvert replacement project through the Queensland Government’s State Road Network Upgrade Program - State-wide structures upgrades (major culvert subprogram).

Investment: ID 2207362

Total investment
$12.16 million
Queensland Government
$12.16 million

Current status

Construction commenced in March 2025 and is expected to take around 12 months to complete, weather and construction conditions permitting.

Esk-Hampton Road, Perseverance Creek, replace culvert project location map

Map of the project area where the culvert will be replaced on Esk-Hampton Road at Perseverance Creek.

Last updated: 16 February 2026